Ostwind 2 grid connection

NKT supports ongoing German energy transition, known as "Energiewende" by delivering a total of almost 300 km of cables with low carbon footprint.

Key facts - Ostwind 2 grid connection

Client

50Hertz

Location of the project

approx. 40 km northeast of the German Island of Rügen in the Baltic Sea

Total cable length

265 km offshore cable (three cable systems), 9 km onshore cable

Duration

2018 - ongoing

Scope

Ostwind 2 grid connection
Ostwind 2 grid connection
Ostwind 2 grid connection
Ostwind 2 grid connection
Ostwind 2 grid connection
Ostwind 2 grid connection

The project

An important contribution to the German “Energiewende”.

The solution

Two production plants enable more efficient production planning and high delivery flexibility.